HomeTrack RecordTalisman Malaysia Bunga Raya

Talisman Malaysia Bunga Raya

For a platform extension of 1,500t, Talisman decided to use SPT Offshore's Self Installing Monopiles (SIMs), a cost efficient and low impact platform extension founded on 2 suction pile based monopods. A critical EPCI schedule of 4 months was met. Because of the suction pile foundation, no driving required next to an operational platform was required, eliminating the risk of damage to the existing facilites.

Scope of Work

  • Design of monopiles and suction pile foundation
  • Marine design and transport and installation engineering
  • Installation of 2 SIMs

Facts and figures

  • Client
    Talisman
  • Year Completed
    2006
  • Location
    Malaysia
  • Suction Piles
    7m OD x 8m deep
  • Topsides Weight
    1,500t on two monopod
  • Monopod Weight
    150t
  • Soil Condition
    Clayey soils
  • Water depth
    55m
  • Project categories
    SIM
+