HomeTrack RecordChevron North Nemba Jacket

Chevron North Nemba Jacket

For Chevron, the North Nemba jacket was installed within 24 hours, including wet upending, set down and suction pile installation. The verticality of the structure was within 0.25 deg due to SPT Offshore's suction pump spread, which is capable of selective and proportional suction on the individual suction piles

Facts and figures

  • Client
    Subsea 7
  • Year Completed
    1999
  • Location
    Angola
  • Suction Piles
    3x 5m OD x 5.5m length
  • Jacket Weight
    650 mT
  • Soil Condition
    Soft Clays
  • Water Depth
    120m
  • Project categories
    Jackets
+