Project management and preparation of installation engineering document for 2 start-up piles. Provison of start-up pile and suction installation services.

SPT achievements

Two sucion piles installed in January 2018 from the Allseas vessel Audacia with the SAPS-003 and removed a year later in January 2019 with the same spread again.

Facts and figures

  • Client
    Allseas
  • Year completed
    2019
  • Location
    Offshore Mediteranian
  • Start-up piles
    OD 3.4m x 9.85m and OD 6m x 6.75m
  • Soil conditions
    Soft clays
  • Waterdepth
    1650m
  • Project categories